1. construction of inlet structure and drain path at j.m. mehsana; 2. extending wing wall and approach at existing box inlet near j.m. mehsana; 3. providing, laying & extending rcc h.p. pipe for construction of existing gamanpura village check dam gamanpura survey no. 1177 (kaklaj talav) j.m. mehsana; 4. construction of box type inlet and providing service for operation of gates and canal regulating and security of structure, including all necessary items for communication system and all necessary items for supply, installation, operation for one year and maintenance of sujalam suflam spreading canal at ch. 254.155 km to ch. 293.630 km (u/s banas river) for the year 2021-22; 5. providing, laying and construction of new weir and construction of samoda-hameerpur-wagpura sub-minor at j.m. mehsana; 6. providing service for operation of gates and canal regulating and security of structure, including all necessary items for communication system and all necessary items for supply, installation, operation for one year and maintenance of sujalam suflam spreading canal at ch. 292.030 km to ch. 230.120 km for the year 2021-22; 7. providing service for operation of gates and canal regulating and security of structure, including all necessary items for communication system and all necessary items for supply, installation, operation for one year and maintenance of sujalam suflam spreading canal at ch. 292.030 km to ch. 274.640 km for the year 2021-22; 8. providing and storing capacity of reservoir (bhemetri) and storing capacity of reservoir (bhemetri) at j.g. vadnagar j.m. mehsana. (guj image)
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.