annual tender for capital works of nd (south area) - ht do rod, earthing rod, helmet, safety belt, hand gloves for lt, hand gloves for ht, other safety items- ht tapping from the existing pole including fixing ofcross arms,, clamps anti-climbing devices, danger board, insulators etc., complete and painting of fabricated materials and numbering, complete withcost of paints as per standard specification but, excluding erection of guy set and earthing., no. 471, 2, erection of psc poles of 8 mt ./200 kg including excavation of pit, and refilling of earth, fixing ofcross arms, top fitting clamps, anti-climbing devices, insulators etc. complete and painting of, fabricated materials used on the poles and numbering with cost, of paint as per standard specification but excluding erection of, guy set and earthing., no. 1141, 3, erection of steel poles of 9 to 11 meters including excavation of, pit and refilling of earth, fixing of cross arms, top fitting, clamps anti-climbing devices, danger board, insulators etc., complete and painting of steel pole, fabricated materials used, on the pole and numbering with cost of paint as per standard, specification but excluding erection of guy set and earthing., no. 1911, 4, erection of steel pole of 13 meters for railway crossing on, bg/mg/ng line for 0.400/11/22kv overhead lines i.e including, excavation of pit & refilling ofearth, fixing cross arms, top, fitting clamps, anti-climbing devices danger board, insulators, etc. complete and painting of steel poles, fabricated materials, used on the poles and numbering with costof paint as per, standard specification but excluding erection of guy sets and, earthing., no. 2190, 5, erection of double pole structure of 8 meters 200 kg psc poles, including excavation of pits & refilling of earthing, fixing of, channels, supporting angles,clamps, anti-climbing devices, danger boards,insulators etc.complete and painting of, fabricated materials used on the poles and numbering with cost, of paint as per standard specification but excluding erection of, guy sets and earthing.(without ab switch), no. 2593, 6, erection of double pole structure of 9 to 11 meters.steel pole, including excavation of pits & refilling of earth, fixing of, channels, supporting angles, clamps,anti-climbing devices, danger boards, insulators etc.complete & painting of, poles,fabricated material sused on the poles and numbering, with cost of paints as per standard specification but excluding, erection of guy set and earthing.(without ab switch), no. 3746, 7, erection of double pole structure with mounting ofab switch,, do fuses of 8 mtrs 200 kg psc poles including excavation of pits, and refilling of earth, fixing of channels supporting angles,, clamps, anti-climbing devices, danger boards, insulators, do, fuses etc. complete and painting of fabricated materials used on, the poles and numbering with costof paint as per standard, specification but excluding of erection of guy set and earthing., (with ab switch), no. 3116p a g e 72 | 86, 8, erection of double pole structure with mounting ofab, switch, do fuses, 9 to 11 meters steel poles including, excavation of pits and refilling of earth, fixing of, channel, supporting angles, clamps, anti-climbing devices,, danger boards, insulators, etc. complete and painting of, poles fabricated materials used onthe poles and, numbering with cost of paint as per standard, specification but excluding erection of guy set and, earthing. (with ab switch), no. 4089, 9, erection of double pole structures with mounting of ab, switch, do fuses, transformers, lightening arrestors,, distribution box. of 8 meters 200 kg and psc poles, including excavation of pits and refilling of earth,, carting of transformers fromstores to site, fixing of, channels, supporting angles, bracings cross arms clamps,, anticlimbing devices, danger boards, conductor and, cable wiring etc.complete and painting of fabricated, materials usedon the poles and numbering with cost of, paint as per standard specification but excluding, erection of guy sets and earthing., no. 8895, 10, erection of double pole structure with mounting ofab, switch,hg fuses transformers, lighteningarrestors,, distribution box 9 to 11 meters steel polesincluding, excavation of pits & refilling of earthcarting of, transformers from store to site, fixingof channels, supporting angles, bracing, cross arms,clamps,, anticlimbing devices, danger boards,conductor and cable, wiring etc. complete andpainting of poles fabricated, materials used on thepoles and numbering as per, standard specificationbut excluding erections of guy sets, and earthing., no. 10400, 11, erection of guy set including excavation of pits &refilling, of earth as per standard specification with stay clamps,, stay wire, anchor rod, turn buckle, eyebolt, guy, insulator, cement concrete block etc. but excluding, concreting., no. 549, 12, concreting of poles, guys, etc. including cost of cement, sand metal (1:2:4) and water etc. as per standard, specification. cement should be opc(53 grade) used for, concreting, cmt 8452, 13, erection of coil type earthing including cost of coalsalt, etc. but without cost of gi wire as per standard, specification (20 kg salt + 20 kg coal), no. 763, 14, erection of plate type earthing including cost of coalsalt, etc. but without cost of gi wire as per standard, specification (20 kg salt + 20 kg coal), no. 766, 15, erection of street light fixture complete withclamps,, brass nipple, brass holder teck wood bush,reflectors fuse,, wiring etc. as per standard specification but excluding, cost of materials., no. 352, 16, stringing of 30mm2 acsr/34mm2,55mm2 aaacconductor, for 11/22kv & lt lines including fixing of insulators,, binding jumpering etc., one, con, d, per, km, 2070, 17 stringing of gi wire 8 swg including binding jumperingetc. do 1159p a g e 73 | 86, 18, providing single phase service connection with pvc2.5/4.0, mm2 twin core cable from terminal pole tometering, point including fixing of meter & complete work as per, standard specification but excluding cost of materials., but including cost of justi khila., no. 389, 19, providing three phase 4 wire service connection withpvc, 4mm2/10mm2 four core cable from terminal poleto, metering point including fixing of meter & complete work, as per standard specification but excluding cost of, materials. but including cost of justi khillas, nuts et, bolts., no. 535, 20, additional cost for excavation of pit in hard rockarea, for erection of pole/ guy etc. as per standard, specification over & above normal cost covered against, excavation of pit under normal soil for erection of pole,, guy, double pole structure earthing with the approval of, supdt.engineer., no. 352, 21 providing guarding to ht line on road/ rail crossing. mtr 69, 22 providing guarding of lt lines on road/rail crossing. mtr 69, 23 lt line tapping- single phase no. 50, 24 lt line tapping- three phase no. 92, 25, laying of overhead lt cable for road crossing,ht line, crossing and telephone line crossing etc.(per span), per, spa, n, 258, 26, erection of single pole structures with, do fuses,, transformers, lightening arrestor, distribution box. on 8, meters 200 kg psc pole including excavation of pits and, refilling of earth, carting of transformers from stores, to site, fixing of channels, supporting angles, bracings, cross arms clamps, anticlimbing devices danger boards,, conductor and cable wiring etc.complete and painting of, fabricated materials used on the pole and numbering, with cost of paint as per standard specification but, excluding erection of guy sets and earthing., no. 4446, 27, erections of single pole structures with mounting of ab, switch do fuses, transformers, lightening arrestor, and, distribution box. on 9 to 11 meters rsj pole including, excavation of pits and refilling of earth, carting of, transformers from stores to site, fixing of channels,, supporting angles, bracings cross arms clamps,, anticlimbing devices danger boards, conductor and cable, wiring etc.complete and painting of fabricated materials, used on the pole and numbering as per standard, specification but excluding erection of guy sets and, earthing., no. 5201, 28, erection of single pole structures with, hg fuses,, transformers, lightening arrestor, distribution box on, existing 8 meters 200 kg psc pole including excavation of, pits and refilling of earth, carting of transformers from, stores to site, fixing of channels, supporting, angles,bracings cross arms clamps, anticlimbing devices, danger boards, conductor and cable wiring etc.complete, and painting of fabricated materials used on the pole and, numbering with cost of paint as per standard, specification but excluding erection of guy sets and, earthing., no. 2894p a g e 74 | 86, 29, erection of single pole structures with , hg fuses,, transformers, lightening arrestor, distribution box on, existing 9 to 11 meters rsj pole including excavation of, pits and refilling of earth, carting of transformers from, stores to site, fixing of channels, supporting, angles,bracings cross arms clamps, anticlimbing devices, danger boards, conductor and cable wiring etc.complete, and painting of fabricated materials used on the pole and, numbering with cost of paint as per standard, specification but excluding erection of guy sets and, earthing., no. 3104, 30, erection of psc poles of 10 mt./ 270 kg including, excavation of pit and refilling of earth, fixing ofcross, arms, top fitting clamps anti-climbing devices, insulators, etc. complete and painting of fabricated materials used, on the poles and numbering with cost of paint as per, standard specification but excluding erection of guy set, and earthing., no. 2669, 31, erection of double pole structure of 10 meters 270 kg psc, poles including excavation of pits & refilling of earthing,, fixing of channels, supporting angles,clamps, anticlimbing devices danger boards,insulators etc.complete, and painting of fabricated materials used on the poles, and numbering with cost of paint as per standard, specification but excluding erection of guy sets and, earthing., no. 5558, 32, stringing of 100mm2 acsr/100mm2 aaac conductor for, 11/22kv & lt lines including fixing ofinsulators, binding, jumpering etc., one, con, d, per, km, 4766, 33, stringing of abc of following sizes including fitting of, all accessories i.e. special design suspensiion/tension, clamp. fixing of crossarm, lt shackle insulator, & directed, by engineer-in-charge., (i) 3x50mm2+16mm2+1x35mm2, (ii)3x50mm2+16mm2+1x25mm2, mtr 34, 34, stringing of abc of following sizes including fitting of, all accessories i.e. special design suspensiion/tension, clamp. fixing of cross arm, lt shackle insulator, etc. for, fixing of messenger wire complete, as required & directed, by engineer-in-charge., (i) 1x35mm2 + 1x25mm2, mtr 17, 35, stringing of 11kv abc of following sizes in rural/urban, area including fixing of cross arm, sspecial design, suspension/tension clamp, binding to pin insulator,, preparing shckle point jumpers etc. as required and, directed by engineer-in-charge., (i) 3x95mm2+1x80mm2, (ii)3x70mm2 + 1x70mm2, mtr 47, 36, stringing of abc of following size including fitting of all, accessories, (i) 2c x 50 + 1c x 25 + 35 sq. mm, mtr 10p a g e 75 | 86, 37, erection of double pole structures with mounting of ab, switch, hg fuses, transformers, lightening arrestors,, distribution box of 10 meters 270 kg and psc poles, including excavation of pits and refilling of earth,, carting of transformers from stores to site, fixing of, channels, supporting angles,bracings cross arms clamps,, anticlimbing devices danger boards, conductor and cable, wiring etc.complete and painting of fabricated materials, usedon the poles and numbering with cost of paint as per, standard specification but excluding erection ofguy sets, and earthing., no. 10171, 38, erection of double pole structure for ctpt unit (psc pole), (erection of double pole structures with ctpt, lightening, arrestors, of 8 meters 200 kg and psc poles including, excavation of pits and refilling of earth, carting of ctpt, fromstores to site, fixing of channels, supporting, angles,bracings cross arms clamps, anticlimbing devices, ,danger boards, conductor and cable wiring etc.complete, and painting of fabricated materials use on the poles and, numbering with cost of paint as per standard, specification but excluding erection of guy sets and, earthing.), no. 6290, 39, erection of single pole shackle point on psc pole 8 mt./200, kg.(erection of psc poles of 8 mt./200 kg including, excavation of pit and refilling of earth, fixing of cross, arms, top fitting clamps anti-climbing devices, insulators, etc. complete and painting of fabricated materials used, on the poles and numbering with cost of paint as per, standard specification but excluding erection of guy set, and earthing), no. 1234, 40, erection of single pole shackle point on steel pole ( 9 to, 11 mtr), (erection of steel poles of 9 to 11 meters including, excavation of pit and refilling of earth, fixing of cross, arms, top fitting clamps anti-climbing devices, danger, board, insulators etc. complete and painting of steel, pole, fabricated materials used on the pole and, numbering with cost of paint as per standard, specification, but excluding erection of guy set andearthing)., no. 2005, 41, erection of single pole shackle point on steel pole(13 mtr), (erection of steel poles of 13 meters including, excavation of pit and refilling of earth, fixing of cross, arms, top fitting clamps anti-climbing devices, danger, board, insulators etc. complete and painting of steel, pole, fabricated materials used on the pole and, numbering with cost of paint as per standard, specification but excluding erection of guy set, andearthing), no. 2284, 42, erection of double pole structure of 13 mtr steel pole, (erection of double pole structure with mounting ofab, switch, do fuses transformers, lighteningarrestors,, distribution box 13 meters steel polesincluding, excavation of pits et refilling of earth carting of, transformers from store to site, fixing of channels, supporting angles, bracing, cross arms,clamps,, anticlimbing devices, danger boards,conductor and cable, wiring etc. complete and painting of poles fabricated, materials used on thepoles and numbering as per, standard specification but excluding erections of guy, sets and earthing.), no. 4659p a g e 76 | 86, 43, erection of double pole structure for ctpt unit(girder, pole) (erection of double pole structure with mounting, of ctpt, lighten ingarrestors, 9 to 11 meters steel, polesincluding excavation of pits et refilling of earth, carting of ctpt from store to site, fixing of channels, supporting angles, bracing, cross arms,clamps,, anticlimbing devices, danger boards,conductor and cable, wiring etc. complete and painting of poles fabricated, materials used on thepoles and numbering as per, standardspecification but excluding erections of guy sets, and earthing.), no. 7795, 44, providing single phase service connection (for solar, generation meter, high rise building, complex etc.)with, pvc 2.5/4.0 mm2 twin core cable from common bus bar to, metering point including fixing of meter et complete, work as per standard specification but excluding cost of, materials., no. 137, 45, providing three phase 4 wire service connections (for, solar generation meter, high rise building, complex etc.), with pvc 4mm2/10mm2 four core cable from bus bar to, metering point including fixing of meter et complete, work as per standard specification but excluding cost of, materials., no. 180, recovery proposed for not providing ab switch & lt distribution box., 46, during the erection of transformer center, if ab switch is, not provided then amount rs.833.00 shall be recover from, the bill of e/o transformer center of contractor., no. 833.00, 47.
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.