casing extension work at mdpl aspl pvpl bppl locations - hpcl is operating a 1054 km long mundra and delhi pipeline (mdpl) for transporting petroleum products from mundra dispatch and pumping station (gujarat) to hpcl installations at palanpur (gujarat), ajmer and jaipur (rajasthan), rewari and bahadurgarh (haryana). mdpl crosses many railway lines, highways and canals and cased crossings have been provided for the same. the scope of work under this tender shall include execution of maintenance, housekeeping, vegetation clearance, repair, restoration, and other associated activities within the right of use (rou) of mdpl pipeline stations as detailed below. all works may be carried out anywhere within the entire rou area of the respective mdpl stations and in accordance with applicable safety standards, statutory requirements, and company procedures. the scope of work includes installation of 24 inch diameter steel casing pipe across the proposed railway crossing location to provide protection to the existing 18 inch mundra delhi pipeline (mdpl) locations.
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.
Eligibility Criteria - Download