e-auction sale notice for sale of immovable assets under the securitisation and reconstruction of financial assets and enforcement of security interest act, 2002. the property is mortgaged/charged to kotak mahindra bank ltd. and physical possession of which has been taken. the sale is on 'as is where is basis', 'whatever there is basis' and 'no recourse basis'. details of immovable property put for e-auction: - mortgagor: praveen kumar jain (huf) - details of immovable property: all that piece and parcel of property being land measuring 1728 sq.ft. carpet (1728 sqft. super built up area) inclusive of proportionate area of common amenities chandralok hsg. complex survey no. 276/p of village chanod near cine park theatre and bank of baroda vapi-sivassa road vapi together with all the present and future superstructures thereon and which is bounded as under: - towards north: 11th feet wide main passage. - the property is for residence.
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.
Eligibility Criteria - Download