sell of scrap coach condemned under age old used and u.s. lying at bg work shop bhavnagar para - as is where is basis - total coach 10 nos - coach no. [1] 084192 gs rcf [2] 047146 slr rcf [3] 063166 wgscn beml [4] 104198 gs icf [5] 064081 gs icf [6] 094262 wgscn beml [7] 114965 gs beml [8] 074180 gs rcf [9] 117124 gslrd rcf [10] 043061 wgscn rcf custodian sse scrap bvp, mode of delivery in number. coaches will be handed over as is where is basis - purchaser should clear the site before final delivery - reclaim parts to be handed over to concern sse at his section in good condition. following items are already reclaimed from the coaches - alternator 4.5kw - 05 nos. ,tensioning device - 05 nos. , bldc fans - 149 nos., fan dc - 01 nos. , night lamp - 35 nos. , elu - 26 nos., rotary board - 07 nos. , battery -120ah - 114 nos., regulator 4.5kw - 06 nos. , cfl light - 18 nos., 2 ft. long tube light - 158 nos., side lamp - 01 nos. , ss bio tank - 34 nos. (coach wise item break out is available with custodian), reclaim parts [a] mechanical items [1] wheelset complete with axle box housing assembly & pulley. - 40 nos [2] bmbc - 40 nos. [3] brake cylinder pipe line - 20 nos. [4] bogie assembly (without wheel sets) - 20 nos. [5] buffer assembly - 36 nos. [6] screw coupling assembly - 2 nos. [7] wearing piece - 40 nos. [b] electrical items [1] battery -120 ah (01 set = 19 nos.) - 02 set. [2] alternator 4.5 kw - 02 nos. loading by purchaser. fdp 50 days.
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.
Eligibility Criteria - Download
No documents uploaded for this tender yet.