corrigendum : supply of - copper cable , cable 4 core , 1c x 1.5 sqmm green earthing cable , complete industrial led high bay , 4 way lighting distribution panel , ms angle size 50x50x5 mm , cable gland 4 core x 16mm2 , control cable gland-4cx2.5 , cable lugs-16sq.mm , 4 sqmm copper lugs , junction box , hot dip galvanized cable tray , mcb 16 amp, , mcb 3 phase 4 pole , work of fabrication , labor charges for removing existing lighting , labor charges for removing existing wiring , laying charges for pvc armoured , work of wiring testing and commissioning , work of connection wiring and drawing , work of fixing connection testing and commissioning , work of fixing cable glanding testing and commissioning , work of installation of hot dip galvanized , work of oprating eot crane , work of preparing scafolding , naming slash numbering of lighting junction box , naming slash numbering of lighting panel - supply erection and commissioning of high bay lights | quantity - 32871
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.
Eligibility Criteria - Download