supply of - drill s.s. twist block , cordless electric drill machine , gi pipe bending machine , brake test arrangement , well type mano meters , bourden tube pressure gauge , valve positioners booster relays , portable-air lpg brazing kit , core drill machine , vernier bevel protractor , marking table surface plate table , blocks vee 150 x 100 x 100 mm , reamer machine , scraper flat , scraper 3 corner , scraper half round , power tool , knurling tool , boring bar indexable , dowel pin , standard tap screws , lapping plate 6 inch dia , medium carbon heat treated alloy steel , caps screws , drills guage straight , drill gauge , globe valve cast iron , gate valve dia , stop cock , pipe mild steel , g.i. pipe , flange slip-on , jigs fixture , pulleys , key , gear - spur old damaged , belt v , washer clutch keys , drift drill , bearing different types , lifting sling , welding cables , table for gas welding , compressor unit suitable for pressure - mechanical tools and equipments and measuring instrument | quantity - 90
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.