supply of - ms square bar 25 , ms angle 40x40x6 , ms roundbar 10 , g i sheet , drill bit set , transformer 12v, 6-0-6, 500ma , capacitor 1000 mfd , capacitor 470 mf, 0.1mf , 8 swg bare copper wire , 20 swg super enemal copper wire , intermidiate switch , lamp 200 w , lamp 100 watt , lamp 60 watt , lamp 240v, 15 watt , copper tube chalk, 40 watt , starter , tube patti with rotary holder , led par light , preset , potentiometre , light detectiv resistant , carbon resistant 1k, 1w , ic 7805 , copper lug 1.5mm2 , thermistor t - 320 , pvc saddle 19mm , pvc saddle 8mm , indicator 6a , main contractor , star contractor , delta contractor , indicating panel lamp r y b , 3 pin top 16 amp , 3 pin top 6 amp , one way switch 16 amp , field book for serveyor , paper canvas , embroidary thread cotton , embroidary ring , measure tape for sewing machine , detan for cosmetology , sun screen cream , hair spa cream , hair serum , hydrogen peroxide - raw material for iti vadali | quantity - 547
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.
Eligibility Criteria - Download