supply of - power tools for fastening , wooden mallet , screw driver diamond insulated head , cordless electric drill machine , gi pipe bending machine , earth electrode primary electrode , earth electrode secondary cu strip , rubber mat , rubber matting , rcc pole with accessories , multifunction meter , star delta strater soft starter , bldc motor with controller , servo motor with resolver , pmsm with controller , mppt based charge controller , elecrical machine trainer , coil winding machine manual , ceiling fan coil winding machine , knife electrician , multi meter , cordless drilling machine , autotransformer , frequency meter , power factor meter , solid state solar based single phase energy meter , three phase kwh meter digital , clamp on meter , magnetic flux meter , meter reading instrument mri , hydrometer , bus bar bending machine , bus bar punching machine , gauge, wire imperial stainless steel marked in swg , contactor and auxiliary contacts , electro magnetic relay with control panel and relay , insulators including hardware fitting , knife switch dpdt fitted with fuse terminals , knife switch tpdt fitted with fuse terminals , various lamps with fittings , cable jointing kit , cable end termination kit , bus bar with brackets , panel accessories , wiring accessories including switchgears , solar traffic light , sound system , solar panels , solar charge controller with manual switch , motion detector , dmx controller , rewinding machine , control panel , electric kettle , immersion heater , a.c. ceiling fan, , ac table fan , demonstration table - electrical items | quantity - 188
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.
Eligibility Criteria - Download