supply of - screw driver set , stand for hanging dresses , auto-clave eletrically heated , thermometer led display , bp indicator , stethoscope , haemoglobin meter , file flat bastard , hammer mallet , straight edge gauge , ac alternator slip ring puller variable , cleaning tray , stud extractor , stud remover , cut section working model , demonstration board of electronic ignition system , working model of power windows , working model of torque converter model of lmv , electric testing screw driver , engineers stethoscope , hollow punch set of seven pieces 6mm to 15mm , piston ring groove cleaner. , radiator cut section , radiator pressure cap lmv , thread pitch gauge metric , abney level , offset scale for cadastral survey , metal cross staff , dumpy level , fire extinguisher , plane table , telescopic alidade , survey plotting scale , current meter - automobile and general group boq | quantity - 70
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.
Eligibility Criteria - Download