supply of - screw driver , terminal screw driver , knife electrician , hammer ball peen , plum bob , spannner set , screw driver set , rawel punch , wooden mallet , conduit pipe cutting and threading machine , hot wire ammeter , wheastone bridge , voltmeter , ammeter , variable auto transformer , energy meter biderctional , kwh meter , kwh meter , kw meter , hydraulic crimping tool , crimping tool , rubber mat , wall jumper , rawl toool holder , foot print grtip , hand vice , safety belt , rubber glows , battery , solar charge controller , motion detector , dc power supply , preventer , field regulator , dc compound motor , dc series motor , electric iron , immerson heater , mixture , rewinding machine , screw driver , hammer cross peen , bearing puller set , mallet , hammer , plier , drill hnad brace , drill ss twist block , plain jack , plain smoothing , file , soldering iron , cut out relay , reverse current relay , laboratory type induction coil , thermometer , knief switch , elcb , rheostate , halogen inandescent lamp , hpmv lamp , low pressure sodium lamp , ohm meter , multimeter , wattmeter , ac energymeter , growller , function generator , ic trainer kit , transformer , motor , screw pitch gauge , drill twist straight shank , filler guage , chuck drill , lapping plate , pulley - tools and equipments procurement | quantity - 396
The tender document is a Request for Proposal (RFP) for selecting a bidder for the Design build finance operate and transfer of cement grinding units. It outlines the terms and conditions for a long-term agreement to construct and operate a cement grinding unit on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis.
Agreement Duration : The agreement is valid for 30 years from the Scheduled Commercial Operation Date (SCOD).
Grant of Concession : The Owner grants the Concessionaire the right to access the project land and perform the scope of work.
Scope of Work : Includes designing, financing, construction, commissioning, stabilization, manufacturing of cement, operation and maintenance of project assets, and packaging and delivery of cement.
Raw Materials and Utilities : The Owner is responsible for providing raw materials and electricity.
Obligations of Concessionaire : Compliance with all applicable laws, maintaining safety standards, and ensuring the project assets meet performance parameters.
Commissioning and Stabilization : Detailed timelines and conditions for commissioning and stabilizing the grinding unit.
Conversion Charges : Payment terms for the conversion charges based on the lowest cost bid accepted by the Owner.
Liquidated Damages : Provisions for delay liquidated damages and shortfall liquidated damages.
Termination : Conditions under which the agreement can be terminated by either party and the consequences of termination.
Dispute Resolution : Any disputes arising under the agreement shall be resolved through arbitration.
Specifications and Standards : As per Ambuja standards
Annual Contracted Quantity of Cement
KPIs of Cement : Key KPIs of cement to be maintained
This document provides a comprehensive framework for the Concessionaire to develop and operate the cement grinding unit, ensuring compliance with all legal, technical, and operational requirements.